The costs per day of reducing the duration of the activities are given in the
table below. Write down the LP to be solved in order to minimize the total cost
of completing the project within 20 days.
Activity Cost per day reducing Max. possible reduction
duration of activity in duration of activity
A Rs 3000 2
B Rs 1500 3
C Rs 2000 1
D Rs 4000 2
E Rs 2000 2
F Rs 3000 3
G Rs 4000 1