Markus Heller <address@hidden> writes:

> Hello,
>
> This is what my project.org looks like:
>
> * STARTED My Project                         :NEXT:   
>   :LOGBOOK:...
>
> ** TODO Task 1 [0/2]
> *** TODO Sub-Task 1
> *** TODO Sub-Task 2
>
> This is what I'd like to do:
>
> I'd like to be able to clock in from Task 1, Sub-Task 1, or Sub-Task
> 2, but make org-mode add the clock entries into the :LOGBOOK: of My
> Project, i.e. the top-level task/project.  In other words, I'm not
> interested in keeping track of how much time I spent on Task 1, or any
> of the sub-tasks, I'm only interested in the time I've spent on
> working on My Project.
>
> Is there anyway to do this?

C-c C-x C-d will total time for a task including times on a subtask.

-Bernt