Hi Peder,
Peder Stray <address@hidden> writes:
> When calling clocktable with :block *month and :step week it splits
> into block 7 days long starting from the first day in the month...
> that's not very useful I think, so here is a patch making it split
> the month into weeks starting on mondays. The first and last week
> will be clipped to only include the days in the selected month and as
> such will not contain the full 7 days of those weeks.
thanks for this idea and for the patch. I just pushed a different
implementation, allowing a new :mstart parameter for clocktables,
similar to the already existing :wstart parameter.
The default for :wstart (the week starting day) is 1, for monday.
The default for :mstart (the month starting day) is 1, for the first
day of the month.
So the new default for e.g.,
#+BEGIN: clocktable :block month :step week
#+END
is to start on the 1st of the month (ignoring :wstart) and to continue
with weeks starting on mondays.
If you use
#+BEGIN: clocktable :block month :step week :wstart 2 :mstart 3
#+END
it will start the report on the 3rd of the month, and continue the
weekly steps starting from tuesdays.
Thanks for this idea and for the patch!
--