From: Daniele Micarelli
Subject: Re: [Help-glpk] help
Date: Fri, 29 Jun 2012 19:14:19 +0200

Re: [Help-glpk] help


it quite
clear
I thank you, because you had many similar constraints and then I solved quite a few errors.
Now I have this barrier
I can not represent this constraint ... I attach the photo

x [i, t] is the variable
I is a set of activities
TC is the set of critical hours
t is the index of TC
d [i] is the duration of the i-th activity

sorry but I am preparing a thesis and I have never used mathprog
thank you very much


2012/6/28 glpk xypron <address@hidden>
Hello Daniele,

sorry got it wrong.

param R;
param T;
set W;
param r{W};
param d{W};
set Q{i in W} := {1-d[i]..T-1};
var x{i in W, Q[i]}, >= 0;
maximize objective:
 sum{i in W, q in Q[i]} x[i,q];
s.t. constraint{t in {1..T}}:
 sum{i in W} sum{q in Q[i]} r[i] * x[i,q] <= R;
data;
set W := a b;
param R := 10;
param T := 5;
param d :=
 [a] 2
 [b] 3;
param r :=
 [a] .5
 [b] .7;
end;

Best regards

Xypron
-------- Original-Nachricht --------
> Datum: Thu, 28 Jun 2012 06:22:13 +0200
> Betreff: Re: [Help-glpk] help

> Hello Daniele,
>
> the following model contains a constraint of the type you refer to.
> Please, read glpk-4.47/doc/gmpl.pdf carefully. It is included in the
> source distribution of GLPK available at
> ftp://ftp.gnu.org/gnu/glpk/glpk-4.47.tar.gz
>
> param R;
> param T;
> param t;
> set Q := { 1..T };
> set W;
> param r{W};
> param d{W};
> var x{W,Q}, >= 0, <=10;
> maximize objective:
>   sum{i in W, q in Q} x[i,q];
> s.t. constraint:
>   sum{i in W} sum{q in Q : q >= t-d[i] && q <= t-1} r[i] * x[i,q] <= R;
> data;
> set W := a b;
> param R := 10;
> param T := 5;
> param t := 6;
> param d :=
>   [a] 2
>   [b] 3;
> param r :=
>   [a] .5
>   [b] .7;
> end;
>
> Best regards
>
> Xypron
> -------- Original-Nachricht --------
> > Datum: Wed, 27 Jun 2012 11:02:27 +0200
> > Betreff: Re: [Help-glpk] help
>
> > Re: [Help-glpk] help
> >
> > I have attached the image so it is clearer
> > W is a set of tasks
> > T is the set of the time allowed
> > r (i) is the parameter of the requested resource the activity i-th
> > d (i) is the duration of the i-th activity
> > R is the parameter that represents the total resource available in the
> > system
> > X (i, q) is the variable
> >
> > Thanks
> >
> >
> > 2012/6/27 glpk xypron <address@hidden>
> >
> > > Hello Daniele,
> > >
> > > from your description it is unclear what you mean by t.
> > >
> > > Is t the run parameter of the summation or is it a parameter
> controlling
> > > the boundaries of the summation? It cannot be both.
> > >
> > > Please, write down your equation completely including the definition
> of
> > > the sets and parameters. Either send it in tex or append an image
> file.
> > >
> > > Best regards
> > >
> > > Xypron
> > >
> > > -------- Original-Nachricht --------
> > > > Datum: Tue, 26 Jun 2012 23:46:10 +0200
> > > > Betreff: Re: [Help-glpk] help
> > >
> > > > Re: [Help-glpk] help
> > > >
> > > > r (i) is a parameter and represents the resource request from the
> i-th
> > > > activities by the system.
> > > > The variable is x (i, t) where i is the index of the activities of
> the
> > > > whole W and t is the index of the time interval.
> > > > R is the total available resource is not exceeded while d (i) is the
> > > > duration of the i.th activity
> > > >
> > > > >
> > > > >
> > > > >
> > > > >> On Tue, 26 Jun 2012, Daniele Micarelli wrote:
> > > > >>
> > > > >>  I have to solve a linear programming problem with the language
> and
> > > I'm
> > > > >>> planning mathprog
> > > > >>> I have difficulty writing the following constraint: ΣΣ r (i) *
> x
> > (i,
> > > > t)
> > > > >>> <= R
> > > > >>> where the first summation is true for all belonging to the W and
> > the
> > > > >>> second
> > > > >>> summation has as its lower end t-d(i) and upper bound as t-1
> > > > >>>
> > > > >>
> > > > >> You've not made it clear what is a variable and what is not.
> > > > >> If r and x are both variables, you are done.
> > > > >> *Linear* programming does not involve products of variables.
> > > > >>
> > > > >> --
> > >
> > > --
> > > NEU: FreePhone 3-fach-Flat mit kostenlosem Smartphone!
> > > Jetzt informieren: http://mobile.1und1.de/?ac=OM.PW.PW003K20328T7073a
> > >
>
> --
> Empfehlen Sie GMX DSL Ihren Freunden und Bekannten und wir
> belohnen Sie mit bis zu 50,- Euro! https://freundschaftswerbung.gmx.de
>
> _______________________________________________
> Help-glpk mailing list
> address@hidden
> https://lists.gnu.org/mailman/listinfo/help-glpk

--
Empfehlen Sie GMX DSL Ihren Freunden und Bekannten und wir
belohnen Sie mit bis zu 50,- Euro! https://freundschaftswerbung.gmx.de

Attachment: IMG_2404.jpg
Description: JPEG image


reply via email to

[Prev in Thread] Current Thread [Next in Thread]