On Mon, Mar 02, 2015 at 01:33:23PM +0100, Paolo Bonzini wrote:
> Looks like there are still a few pull requests pending, and Peter is on
> vacation.  Should we really enter hard feature freeze tomorrow?  The 2.3
> planning page in the end never got out the "draft" state.
> 
> A possible alternative schedule could be:
> 
> 2015-03-10    Tag v2.3.0-rc0
> 2015-03-17    Tag v2.3.0-rc1
> 2015-03-24    Tag v2.3.0-rc2
> 2015-03-31    Tag v2.3.0-rc3
> 2015-04-03    Tag v2.3.0      (or -rc4, with release on April 7th)
> 
> In this case maintainers should still try not to post new non-bugfix
> pull requests for the coming week, while the pending ones are sorted out.

Delaying makes sense to me.