From: | Markus Heller |
Subject: | [Orgmode] Re: Only Clock in Top-Level Task |
Date: | Thu, 12 Nov 2009 10:48:05 -0800 |
User-agent: | Thunderbird 2.0.0.23 (Windows/20090812) |
Bernt Hansen wrote:
Markus Heller <address@hidden> writes:Hello, This is what my project.org looks like: * STARTED My Project :NEXT: :LOGBOOK:... ** TODO Task 1 [0/2] *** TODO Sub-Task 1 *** TODO Sub-Task 2 This is what I'd like to do: I'd like to be able to clock in from Task 1, Sub-Task 1, or Sub-Task 2, but make org-mode add the clock entries into the :LOGBOOK: of My Project, i.e. the top-level task/project. In other words, I'm not interested in keeping track of how much time I spent on Task 1, or any of the sub-tasks, I'm only interested in the time I've spent on working on My Project. Is there anyway to do this?C-c C-x C-d will total time for a task including times on a subtask. -Bernt
Hi Bernt,I saw this option in the manual, but this is not quite what I want. What I'd like to be able to is clock in from any sub-task and be clocked into the *top-level* task, not the task I'm clocking in from.
Is that feasible? Or am I too confusing? Thanks Markus
[Prev in Thread] | Current Thread | [Next in Thread] |