Hi Bastien and Luke,
Bastien wrote:
> Luke Crook <address@hidden> writes:
>> Is it possible to specify estimated effort in something other than hours
>> (0.5, or 0:30)?
>
> No, it's not possible right now.
But I second this idea: that'd be a great addition. Too often, we have to play
with figures such as 64:00 or 80:00 just to indicate 8 or 10 days...
Being able to specify suffixes like `d' for days or `w' for weeks would be
awesome. But I guess it's very, very complex, though.
Best regards,
Seb
--