Hi Andrew,
"Andrew M. Nuxoll" <address@hidden> writes:
If you do that, I may have to send you a cheesecake.
Time for a cheesecake!
You can now use a "delay cookie" like this:
SCHEDULED: <2013-02-07 jeu. -2d>
The item will not be shown today, but in three days.
See the new options `org-scheduled-delay-days' and
`org-agenda-skip-scheduled-delay-if-deadline' which
are quite symmetric to `org-deadline-warning-days'
and `org-agenda-skip-deadline-prewarning-if-scheduled'.
Thanks for this idea, and thanks to Michael for the
implementation example -- I implemented it a bit
differently, but I think it makes sense (1) to use
-2d to tell the scheduled item is postponed, and
(2) to use the same "-" for prewarning and delays.