Re: org-contrib: Taskjuggler effort calculated via org instead of TJ3?
From: |
Tim Cross |
Subject: |
Re: org-contrib: Taskjuggler effort calculated via org instead of TJ3? |
Date: |
Wed, 22 Jan 2020 10:54:51 +1100 |
User-agent: |
mu4e 1.3.6; emacs 27.0.60 |
Benjamin Kästner <address@hidden> writes:
> Hi,
>
> On version 9.3 (9.3-elpaplus @
> $HOME/.emacs.d/elpa/org-plus-contrib-20191203/), `ox-taskjuggler'
> exports the :Effort: property calculated via
> `org-duration-to-minutes', e.g. 2d get exported as 48.0h instead of
> the literal 2d.
>
> This is unexpected and makes the Taskjuggler export unusable for me in
> the current form. Is there a rationale for this? Maybe I'm missing
> something and it's more reasonable to plan in working hours instead of
> working days. Otherwise, could that behaviour get changed or at least
> put behind a variable/customize interface?
>
> Regards,
> Benjamin
>From memory, I seem to recall that this had something to do with the
ambiguous understanding of what 2d really meant i.e. 48 hours, 16 hours
(assuming 8 hour work day).
I have no opinion regarding which is better, but I don't use taskjuggler
any more (due to other 'limitations' with the export/configuration which
I just cannot recall now - it was many years ago).
Tim
--
Tim Cross