Hello Arne,
Thank you for your reply and advice. :)
"Dr. Arne Babenhauserheide" <arne_bab@web.de> writes:
> Do I understand it right that what you need is to track the time
> required to reach milestones, not following the *progress*?
Well, what I want by "follow the progress" is to see:
* How many work I have done
* How many work remains to be done
* How many time left
* How many time other project need
I want to avoid spending to much time on a project sufficiently finished
to the detriment of another project. Or, if no project can be finished,
do enough of work to have a not so bad grade.
As you suggest, having milestone with their own deadline seems to be a
great idea. A better idea that having one big task for representing an
entire project (like I wanted to do). I will try using effort
estimation. But I will avoid customizing too much Org-mode. In the past,
I ended up several times with a too much complex workflow.
I think I will make a "Project" workflow. Something simple:
* Each project is a headline with the status "PROJECT"
* Each project have the deadline defined by the school work deadline
* Each project have a complete description with every info needed to work
* Each project have one or many tasks (as sub headlines with a status)
* Each task have a importance, time and effort estimation
* Each task have its own deadline, distributed along the remaining time
* When I set a task deadline, I look at its estimations and also other projects
tasks
* To create a new project, I use Org-capture with a template
Every time I create a new project, it start with one task: "Planning the
project". With a deadline at 2 days max. The description of this task is
a checkbox list of thing to do when planning the project.
And finally, 2 times per week, I got a repetitive task: "Review the
projects progress". With this, I should be able to adjust spending time
and effort.
I think it would be simple and need only a few Org-mode configurations.
And by doing like that, every time I look at the agenda, I will see what
work I need to do every days. Task of each project or review of all
projects.
"Dr. Arne Babenhauserheide" <arne_bab@web.de> writes:
> [[PGP Signed Part:Undecided]]
> Hello Seb,
>
> It sounds like org-mode can be a great fit.
>
> Sébastien Gendre <seb@k-7.ch> writes:
>> But, as a student, I regularly have big and important projects to do for
>> the school. The kind of project who need several days to be done, with
>> deadlines too soon, and if you fail one them the consequences can be
>> disastrous. And generally, I have to many of these project in the same
>> time and not enough time to do all the work. So, I also need to follow
>> the progress of each project to choose which is sufficiently advanced to
>> be stop for the benefit of another less advanced project.
>
> Do I understand it right that what you need is to track the time
> required to reach milestones, not following the *progress*? So following
> progress seems like it would take more mental bandwidth than needed.
>
> You could have one org-mode task (headline) per milestone, with a
> DEADLINE (org-deadline), and then SCHEDULE (org-schedule) appointments.
>
> To track how much time you will still need, you can use org-set-effort.
> I did that at work for a while to train to get better at estimating. By
> having the effort in a clocktable I could see progress *when needed*.
> Hitting R in the org-agenda shows the clockreport-mode and you can see
> the Effort in the agenda by setting
> (org-agenda-clockreport-parameter-plist (quote (:link t :maxlevel 2
> :properties ("Effort")))). For a while I had the clocktable active by
> default.
>
> You can also add that to the column-mode (org-columns) to get a quick
> overview for a file (leave with org-columns-quit). Customize:
> (org-columns-default-format
> "%25ITEM %TODO %3PRIORITY %TAGS %17Effort(Estimated Effort){:} %CLOCKSUM")
>
>> And I don't know how to manage this kind of projects with Org-mode. How
>> to do it, without failing a 6 days project because I spent to much time
>> on something else and I have only 3 days left with 3 half-day important
>> appointment I cannot cancel. I can't risk failing a single one of these
>> project by trying. So, when I am in a period with a lot of these
>> projects, I stop using Org-mode and concentrate on doing these project
>> as fast as I can. And because I often have this kind of project, I spend
>> most of the year without being able to use Org-mode.
>
> I found that org-mode is the only organization tool for which using the
> tool actually reduces the time I need for organization. That works by
> taking notes in org-mode, too, and keeping it simple.
>
> What I do:
>
> ** Custom starting point: agenda-with-kanban
> A function to show the agenda it besides the Kanban table. I start
> each day and after each larger break by hitting F12. It shows me the
> agenda and entry points into my work. This enables me to stay focussed.
>
> ** One planning file
> I have a single file for all my tasks. That keeps working
> surprisingly long. Once a year or so it needs some cleanup to become
> faster again.
>
> ** Kanban Table at the top
> I have a kanban table. It shows as most important information the
> tasks I am doing right now. If I am doing more than three work-tasks
> at the same time, it’s warning sign that I’m becoming inefficient.
> With this I start every day in org-mode by clicking on the link of the
> project from the kanban table to get to its notes (which I also track
> in org-mode). See
> https://www.draketo.de/light/english/free-software/el-kanban-org-table
> → https://hg.sr.ht/~arnebab/kanban.el
>
> ** Capture tasks for Projects
> Projects have as many tasks as I need to track. At work they are
> usually Stories (3-5 days). Nowadays I create new tasks by using
> org-capture templates with one template per larger project and one for
> bugs, but I used to just use two templates (which might be a
> better fit for you):
> - (i) task to start immediately and
> - (l) task to start later
>
> ** Setup
>
> (with-eval-after-load 'org
> (setq org-agenda-custom-commands
> '(("o" "Agenda and TODOs"
> ((agenda) ; nil ((org-agenda-compact-blocks
> nil)(org-agenda-block-separator ?-)(org-agenda-overriding-header "")))
> (tags-todo "-notodo-TERMIN" ((org-agenda-block-separator ?-)))
> (tags "KANBAN" ((org-agenda-block-separator ?-)
> (org-agenda-compact-blocks nil)
> (org-agenda-overriding-header ""))))))))
> (defun my/org-agenda-show-kanban ()
> (interactive)
> (save-excursion
> (search-forward ":KANBAN:")
> (org-agenda-goto)
> (org-narrow-to-subtree)
> (show-all)
> (fit-window-to-buffer)
> (widen)
> (recenter-top-bottom 0)))
>
> (defun agenda-and-todo ()
> (interactive)
> (org-agenda nil "o")
> (delete-other-windows)
> (my/org-agenda-show-kanban)
> ;; desktop systemsettings shortcuts: map f12 to
> ;; emacsclient -e '(progn (show-frame)(agenda-and-todo))'
> (global-set-key (kbd "<f12>") 'agenda-and-todo)
>
>
>
>> So, if you have any suggestion on how to manage, in Org-mode, projects
>> with:
>> * Lot of work to do (many days)
>> * Short deadline (not enough time)
>
> This is something to fix. Also outside org. Always feeling like having
> to catch-up can burn you out otherwise.
>
> As an analogy: Even if you have to sprint sometimes, what you really
> want to do is to take a brisk walk, so you can still talk to your fellow
> students and think about the best way to address the tasks — do things
> well thought-out.
>
>> * High importance (disastrous consequences in my future in case of fail)
>> * Many of them in the same time
>> * Progression need to be followed to chose where to sacrifice time to
>> limit the damages
>
> Ideally have a plan beforehand which things to drop when time becomes
> tight. For example tag them or such. These are optional, otherwise you
> could not drop them when times becomes tight.
>
>
>
> (also I have a nicer clocktable layout so level2-entries look good:
>
> ;; nicer org clocktable layout
> (defun my-org-clocktable-indent-string (level)
> (if (= level 1)
> ""
> (let ((str "└"))
> (while (> level 2)
> (setq level (1- level)
> str (concat str "──")))
> (concat str "─> "))))
> (advice-add 'org-clocktable-indent-string :override
> #'my-org-clocktable-indent-string)
> )
>
> Here’s the relevant part of my org-agenda setup:
>
> (use-package org-agenda
> :defer 8
> :custom
> ;; provide desktop alerts, so I can have appointments in org-mode, too
> (alert-default-style 'libnotify)
> (appt-disp-window-function 'alert-for-appt)
> (org-agenda-include-diary t)
> (appt-delete-window-function (lambda ()))
> (org-agenda-clockreport-parameter-plist (quote (:link t :maxlevel 2
> :properties ("Effort"))))
> (org-columns-default-format
> "%25ITEM %TODO %3PRIORITY %TAGS %17Effort(Estimated Effort){:} %CLOCKSUM")
> (org-global-properties
> '(("Effort_ALL" . "0:30 1:00 2:00 3:00 6:00 8:00 16:00 40:00")))
> (org-agenda-start-with-clockreport-mode t)
> :config
> ;; Rebuild the reminders everytime the agenda is displayed
> (add-hook 'org-agenda-finalize-hook (lambda () (org-agenda-to-appt t)))
> ;; Run once when Emacs starts
> (org-agenda-to-appt t)
> ;; Activate appointments so we get notifications
> (appt-activate t)
> (defun appt-reparse-diary-file ()
> "force reparsing the diary file"
> (appt-check t))
> (add-to-list 'midnight-hook 'appt-reparse-diary-file))
>
>
> Best wishes,
> Arne