Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks
From: |
Blue Swirl |
Subject: |
Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away) |
Date: |
Sun, 25 Sep 2011 17:31:53 +0000 |
On Sun, Sep 25, 2011 at 4:48 PM, Avi Kivity <address@hidden> wrote:
> On 09/25/2011 07:36 PM, Blue Swirl wrote:
>>
>> On Sun, Sep 25, 2011 at 2:10 PM, Avi Kivity<address@hidden> wrote:
>> > On 09/24/2011 11:05 AM, Blue Swirl wrote:
>> >>
>> >> On Thu, Sep 22, 2011 at 12:34 AM, Anthony
>> >> Liguori<address@hidden>
>> >> wrote:
>> >> > Consider this a friendly reminder that we're only three weeks
>> >> away from
>> >> > the
>> >> > soft feature freeze for 1.0. I've written a wiki page about my
>> >> > expectations
>> >> > for the soft feature freeze. It's inlined here for easier
>> >> commenting.
>> >>
>> >> I think the freezes and the release should be delayed until the memory
>> >> API conversion is finished, deliberately shipping semi-broken code
>> >> just to satisfy schedules does not benefit anyone but the schedule
>> >> creator. It looks to me that converting all buses and devices might be
>> >> finished by the deadline but it may as well take a bit more until
>> >> everything works again.
>> >>
>> >
>> > There is a difference between "incomplete conversion" and "semi-broken
>> > code". Any breakage should be fixed promptly, but after some freeze
>> > date
>> > (not sure if this is the one proposed), additional conversions would be
>> > pushed to 1.1.
>>
>> Well, there's PPC VGA which is semi-broken by the incomplete conversion.
>
> Please point out a test case and I'll try to fix it.
Run qemu-system-ppc without any arguments. There is a black bar
(because of vga.chain4), it shouldn't be there.
- [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Anthony Liguori, 2011/09/21
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/24
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/25
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/25
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/25
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away),
Blue Swirl <=
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/26
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/27
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Avi Kivity, 2011/09/27
- Re: [Qemu-devel] [FYI] Soft feature freeze for 1.0 is 10/15 (three weeks away), Blue Swirl, 2011/09/27