Marcel van der Boom <address@hidden> writes:
> Hi all,
>
> I've run into an annoyance wrt the :ORDERED: property and the blocking
> of tasks due to it.
>
> Here is the minimal usecase:
>
> ---
> * TODO Project like header, containing subtasks
> :PROPERTIES:
> :ORDERED: t
> :END:
> ** TODO This item is the first to be done in the project
> This one is not blocked, as I expect.
ok
> ** TODO Next task with subtasks
> This is blocked by the sibling above, which is what I expect
ok
> *** TODO Subtask of a blocked sibling.
> This seems to be blocked and I can't understand why. Marking it DONE
> would not mark the parent
> done (neither explicit nor implicit). Why is it blocked then? Bug?
This is blocked until you mark the first level 2 TASK as DONE. The
entire subtree is blocked by the previous incomplete task.
> *** TODO Second item in the blocked
> This is also blocked, which could be right, because the parent
> project has an ordered property and the sibling above is not yet
> complete.
> ---
>
> Should the first task in a subproject of a project
> having the ':ORDERED:' property set to true be blocked from marking
> 'DONE'? If so, why?
I think the answer is yes it should be blocked because the entire tree
is blocked - the previous task needs to be DONE first. When the subtree
is unblocked you can then complete the first task in the subtree.
-Bernt
>
> The above minimal case is easy, but it's far from trivial to see why
> tasks in projects are blocked if the project is longer and has more
> outline levels.
>
> My expectation of the ordered property would be that it only acted
> one-level deep, regarded from a 'block-or-not' standpoint.
>
> Thoughts?
--
Bernt
- [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Marcel van der Boom, 2011/06/20
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?,
Bernt Hansen <=
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Marcel van der Boom, 2011/06/21
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Memnon Anon, 2011/06/21
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Bernt Hansen, 2011/06/21
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Marcel van der Boom, 2011/06/21
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Carsten Dominik, 2011/06/21
- Re: [O] Subtasks are blocked in todo-items of ordered projects. Bug?, Carsten Dominik, 2011/06/21
- Re: [O] [PATCH] Subtasks are blocked in todo-items of ordered projects. Bug?, Marcel van der Boom, 2011/06/21