Re: How do you manage complex project with Org-mode
From: |
Ihor Radchenko |
Subject: |
Re: How do you manage complex project with Org-mode |
Date: |
Sun, 20 Mar 2022 13:06:48 +0800 |
Sébastien Gendre <seb@k-7.ch> writes:
> So, if you have any suggestion on how to manage, in Org-mode, projects
> with:
> * Lot of work to do (many days)
> * Short deadline (not enough time)
> * High importance (disastrous consequences in my future in case of fail)
> * Many of them in the same time
> * Progression need to be followed to chose where to sacrifice time to
> limit the damages
I think that your existing system is already a good starting point. I
would not recommend changing it drastically. Every possible time
management workflow must be based on existing workflow habits (like
daily inbox review) and only introduce new habits one by one and slowly.
For your specific situation with many simultaneous important projects,
you are not alone. Every student meets similar issue.
My recommendations for managing multiple projects:
1. Similar to daily inbox review, do weekly/bi-weekly project progress
review. You are already doing this. However, I am not sure about the
details.
When doing project review, I find it useful to create a custom agenda
listing all the ongoing projects.
Every time I review the project list, I select up to 3 projects I
plan to work on from now till the next project review. All other
projects are marked "HOLD" and their tasks will never be listed in
agenda (unless there is some hard deadline or unskippable meeting).
Review is the time when you decide which projects to sacrifice if you
have insufficient time. Coming back to those HOLD projects after the
review time is a no-no, unless you complete the planned projects and
still have remaining time.
2. If you cannot complete a project within initially planned time, it
may be tempting to continue until completion. Do not do this. It is
better to try finishing the other planned project work first and come
back to the partially completed projects if time permits.
In Org, there are several tools you can use to address this:
- You may dedicate each single day to no more than a single project.
The project tasks will be scheduled to specific days and you can
create a custom agenda that does not show tasks scheduled in past
days.
- You may use effort estimates for projects/tasks shorter than a day
+ non-nil org-clock-sound. If you create a habit to clock-in
regularly, Emacs will play a sound when you run out of time.
- You may create a rule to have at least a single easy 2-3 min task
as "entry" point to a project you plan to switch to. Having a
simple task really makes it easier to switch from working on
current and already familiar project to other one.
*This rule sounds obvious and simple, but I cannot stress more how
much it changed my workflow once I got to follow this regularly*
The above suggestions are simple to list and somewhat obvious, but
not-so-easy to master. It is important to stick to them as much as
possible until they become a habit. They may take months to master.
> To manage school big work, I think of managing them as projects.
>
> I want to apply a simple "Project" workflow:
>
> * Each project is a headline with the status "PROJECT"
> * Each project have the deadline defined by the school work deadline
> * Each project have a complete description with every info needed to work
> * Each project have one or many tasks (as sub headlines with a status)
> * Each task have a importance, time and effort estimation
> * Each task have its own deadline, distributed along the remaining time
> * When I set a task deadline, I look at its estimations and also other
> projects tasks
> * To create a new project, I use Org-capture with a template
Just one comment. If you tend to have a large number of tasks in your
agenda, you are likely overusing deadlines and scheduling. I would avoid
setting deadlines for every single task. Too long agenda lists are
*counterproductive* in many ways. I recommend scheduling the whole
project (or subproject, it the main project is huge) + 1-2 individual
tasks. When you complete the 1-2 individual tasks, it is more productive
to look inside the project, and select next tasks depending on the new
results from the first tasks.
Hope my comments are useful.
Best,
Ihor
Re: How do you manage complex project with Org-mode, Antonio Carlos Padoan Junior, 2022/03/01
Re: How do you manage complex project with Org-mode, Milan Zamazal, 2022/03/01
Re: How do you manage complex project with Org-mode, Quiliro Ordóñez, 2022/03/02
Re: How do you manage complex project with Org-mode, Sébastien Gendre, 2022/03/02
Re: How do you manage complex project with Org-mode, Sébastien Gendre, 2022/03/02