GDP status July 2008
From: |
Graham Percival |
Subject: |
GDP status July 2008 |
Date: |
Fri, 27 Jun 2008 21:35:56 -0700 |
There's two months left in GDP. I'd like to reserve one month for
final clean-up and whatnot, so that leaves one month for the bulk
of the work.
Here's my list of what I'm hoping people to finish in July. If you
don't think you can accomplish it, let me know; I should be able to
shift some people around to cover things. A few sections are very
close to being finished, so those helpers could help other sections in
the second half of the month.
Carl: review NR 1+2 sections as needed, Chords, Rhythms.
Trevor: NR 3, LM 5, any updates to LM 3-4.
Patrick: Expressive.
Ralph: Repeats.
Francisco: Simultaneous.
Till: Staff.
Valentin: Text, LSR as needed.
Neil: LSR as needed, \markup, extra technical stuff.
Kurt: Glossary support. (I don't expect Ancient to be finished)
Andrew: Keyboards.
Jonathan: Fretted strings.
Stefan: Percussion.
John + Reinhold: make texi2html output the default.
This leaves three sections untouched: Vocal, Unfretted strings,
Wind. Hopefully these can be filled by people who finish their
current sections in the next week or two.
Cheers,
- Graham
- GDP status July 2008,
Graham Percival <=